Find out the time required to complete the following project and the critical activities:....
The time taken by an activity in a project network follows a distribution with a standard deviation of one sixth of the range, approximately.....
Programme Evaluation and Review Technique (PERT) is a tool that would help a project manager in project planning and control.....
Determine the critical path, the critical activities and the project completion time.....
The critical path method (CPM) aims at the determination of the time to complete a project and the important activities on which a manager shall focus....
Construct the network diagram for a project with the following activities:....
Certain key concepts pertaining to a project network are described below: ....
Determine the minimum spanning tree for the following network.....
Tree: A minimally connected network is called a tree. If there are n nodes in a network, it will be a tree if the number of edges = n-1.....
Looking at the diagram, we see that node 1 is the origin and the nodes 2 and 3 are neighbours to the origin. Among the two nodes, we see that node 2 i....
Imagine a salesman or a milk vendor or a post man who has to cover certain previously earmarked places to perform his daily routines.....
Finding the EOQ with shortages and the replenishment of inventory is at a finite rate....
E.B.Q with known demand, shortages is permitted and replenishment of inventory is instantaneous....
Determination of the optimum batch quantity [EBQ] if the demand is known and uniform with a finite rate of replenishment....
As we have already classified the economic order quantity or economic batch size problems into two types, based on the demand position. ....
In this section, let us gain some idea about various costs and terminology associated with Inventory Management.....
Based on the reasons, for which the inventory is accumulated, it can be classified into the following categories.....
Any firm would like to hold inventory at specific level to meet smooth, uninterrupted production schedule or to cater consumer demand in case of whole....