Determine the critical path, the critical activities and the project completion time.
Problem
1
The
following details are available regarding a project:
Determine the critical path, the critical
activities and the project completion time. Solution First let us construct the
network diagram for the given project. We mark the time estimates along the
arrows representing the activities. We obtain the following diagram:
Consider the paths, beginning
with the start node and stopping with the end node. There are two such paths
for the given project. They are as follows:
Compare
the times for the two paths. Maximum of {22,19} = 22. We see that path I has the
maximum time of 22 weeks. Therefore, path I is the critical path. The
critical activities are A, B, D and F. The project completion
time is 22 weeks. We notice
that C and E are non- critical activities. Time for
path I - Time for path II = 22- 19 = 3 weeks. Therefore, together the non-
critical activities can be delayed upto a maximum of 3 weeks, without delaying
the completion of the whole project. Problem
2 Find
out the completion time and the critical activities for the following project: In all, we identify 4 paths, beginning with the start node of 1 and
terminating at the end node of 10. They are as follows:
Compare the times for the four paths. Maximum of
{42, 43, 45, 47} = 47. We see that the following path has the maximum time and
so it is the critical path:
The
critical activities are C, F, J and L. The non-critical activities are A, B, D,
E, G, H, I and K. The project completion time is 47 units of time. Problem 3
Draw the
network diagram and determine the critical path for the following project:
Solution We have the following network
diagram for the project:
Solution We assert
that there are 4 paths, beginning with the start node of 1 and terminating at
the end node of 9. They are as follows:
Compare the times for the four
paths. Maximum of {16, 22, 16, 13} = 22. We
see that the following path has the maximum time and so it is the critical
path:
The
critical activities are B, E, I and K. The non-critical activities are A, C, D,
F, G, H and J. The project completion time is 22 weeks.
Tags : Operations Management - Network Problems
Last 30 days 34116 views