The time taken by an activity in a project network follows a distribution with a standard deviation of one sixth of the range, approximately.
Measure Of Certainty
The 3 estimates of time are such
that
t o ≤ t m ≤ tp
Therefore the range for the time
estimate is t p − to .
The time taken by an activity in a project network
follows a distribution with a standard deviation of one sixth of the range,
approximately.
The certainty of the time estimate of an activity
can be analysed with the help of the variance. The greater the variance, the
more uncertainty in the time estimate of an activity. Problem 1 Two experts A and B examined an activity and
arrived at the following time estimates.
Determine which expert is more
certain about his estimates of time:
So, the
variance is less in the case of A. Hence, it is concluded that the expert A is
more certain about his estimates of time.