We can consider (i) Earliest Start Time of an activity and (ii) Earliest Finish Time of an activity.
Key
concepts
Certain key concepts are
introduced below.
Earliest Times Of An Activity
We can consider (i) Earliest Start Time of an
activity and (ii) Earliest Finish Time of an activity.
Earliest Start Time of an activity is the earliest
possible time of starting that activity on the condition that all the other
activities preceding to it were began at the earliest possible times.
Earliest Finish Time of an activity is the earliest
possible time of completing that activity. It is given by the formula.
The Earliest Finish Time of an activity = The
Earliest Start Time of the activity + The estimated duration to carry out that
activity.
LATEST TIMES OF AN ACTIVITY
We can consider (i) Latest Finish Time of an
activity and (ii) Latest Start Time of an activity.
Latest Finish Time of an activity is the latest
possible time of completing that activity on the condition that all the other
activities succeeding it are carried out as per the plan of the management and
without delaying the project beyond the stipulated time.
Latest Start Time of an activity is the latest
possible time of beginning that activity. It is given by the formula
Latest Start Time of an activity = The Latest
Finish Time of the activity - The estimated duration to carry out that
activity.
TOTAL FLOAT OF AN ACTIVITY
Float seeks to measure how much delay is acceptable.
It sets up a control limit for delay.
The total float of an activity is the time by which
that activity can be delayed without delaying the whole project. It is given by
the formula
Total Float of an Activity = Latest Finish Time of
the activity - Earliest Finish Time of that activity.
It is also given by the formula
Total Float of an Activity =
Latest Start Time of the activity - Earliest Start Time of that activity.
Since a delay in a critical activity will delay the
execution of the whole project, the total float of a critical activity must be
zero.
EXPECTED TIMES OF AN EVENT
An event occurs at a point of time. We can consider
(i) Earliest Expected Time of Occurrence of an event and (ii) Latest Allowable
Time of Occurrence an event.
The Earliest Expected Time of Occurrence of an
event is the earliest possible time of expecting that event to happen on the
condition that all the preceding activities have been completed.
The Latest Allowable Time of Occurrence of an event
is the latest possible time of expecting that event to happen without delaying
the project beyond the stipulated time.
Tags : Operations Management - Network Problems
Last 30 days 1279 views